Construction is underway on a 17,444-square-foot logistics facility at Hanscom Air Force Base that will replace two adjoining buildings and consolidate operations for the 66th Logistics Readiness Squadron.

The base spans parts of Lexington, Concord, Bedford and Lincoln.

The new warehouse is scheduled to become fully operational in spring 2027, according to Hanscom AFB. It will replace a supply building from the 1950s and an administrative building from the 1980s. A congressional military construction appropriation funded the project.

"The main building was originally intended to be temporary, but it has remained in service for decades," said Stephen Morin, 66th Logistics Readiness Squadron director. "This new facility will give our personnel the modern workspace and infrastructure needed to better support today's logistics mission."

The project will bring administrative offices, cargo operations and equipment storage together under one roof. It will also include a dedicated hazardous materials storage area with a separate ventilation system and specialized lighting to reduce ignition risks in the event of a gas leak.

Anthony Maressa, a project engineer with the U.S. Army Corps of Engineers New England District, described the kinds of materials the space will hold.

"We will have aerosol cans, motor oil and flammable solvents like paint thinner in that room," Maressa said. "These are common materials you would find in a mechanic shop or even at home, but this room is specifically designed to store them safely."

A carpentry shop with a modern dust collection system will also move into the new building. The existing shop sits on the opposite side of the installation. LRS officials said the shop supports construction of specialized shipping containers and protective materials for transporting mission equipment.

As of mid-November, the roof, exterior walls, doors, windows and interior flooring were nearing completion. Interior work is scheduled to continue through the winter.